By Jerry Morgan, Reporter

DESDEMONA -- Only a relatively small crowd attended the FM 2214 public meeting conducted by the Texas Department of Transportation (TxDOT) last Thursday evening, July 12. There were almost as many TxDOT officials and employees at the meeting as there were area residents for the informational and public involvement session.

A large aerial photo mosaic was placed on the wall of the Desdemona Activity Center above tables that had plans rolled out for public viewing. Four different TxDOT officials took part in different portions of the presentation and answered questions posed by the attendees. They emphasized that the plans shown and discussed are only preliminary, and that no right of way acquisition activity will occur until the plans are finalized, likely not until sometime in 2008.

The 5.3 mile road widening project on FM 2214 will run from near the intersection with Highway 571 north of Desdemona and continue south to the intersection with Highway 8, just west of downtown, and then follow Highway 8 across Hog Creek and through downtown to the intersection of Highway 8 and Highway 16. The purpose of the project is to improve safety by widening, flattening and straightening the roadway to accommodate growing traffic volumes running between Eastland and Stephenville. Both increased truck and college-related traffic have made the currently narrow roadway more dangerous as an average of more than 1,000 vehicles drive on it daily.

In the mostly rural portion of the project, the paved roadway will increase from 23 feet to 40 feet, although it will remain only two lanes. The total right of way will be increased from the current 100 feet to 200 feet. A total of 29.4 acres are projected to be needed for the increased right of way, with the total estimated cost of acquisition to be $936,000. Eastland County will be called upon to fund 10% of the land acquisition costs. The total number of landowners affected is estimated to run from 22-27.

One of the bigger changes that will be involved in the project will be that at the Highway 2214/Highway 8 intersection, Highway 8 traffic northbound from Gorman will be required to stop while southeast bound Highway 2214 traffic proceeds into Desdemona, opposite the current traffic arrangement. The road project will also involve widening the bridge over Hog Creek, but will not involve a teardown and replacement.

No additional right of way will be needed in the downtown Desdemona area. There will be some construction work in the downtown area, however, to facilitate proper drainage and to provide proper handicapped access to buildings and stores. Curbs and gutters may be installed.

One meeting attendee expressed hope that the project would not "mess up downtown" Desdemona similar to what has occurred in Lingleville. A TxDOT area engineer replied that there will be some construction disruptions.

Another meeting attendee noted that not many affected landowners were present at the meeting, and TxDOT officials noted that most of them had already been contacted and given the opportunity to review the plans. No residential relocations are projected to be necessary, either in the rural or in the town portion of the project.

The estimated budget for the project is $5 million, with bid letting planned for late 2012.

 

For all the De Leon news, articles and columns:

Subscribe to the De Leon Free Press